Method Statement 2.24 - Working in Category "O" (Low Risk) Confined Space¶
Document Information
| Field | Value |
|---|---|
| Document Reference | MS 2.24 |
| Issue Number | 2 |
| Issue Date | 1 June 2026 |
| Next Review | 1 June 2027 |
| Prepared By | Sean Ashton |
| Approved By | Aaron Mason, Director |
| Task No | Task | PPE to be worn | Plant required | Reference is made to the Team Pack risk assessment |
|---|---|---|---|---|
| 2.24 | Working in Category "O" (Low Risk) Confined Space | As defined by on-site risk assessment | Calibrated 4-gas monitor, Communications equipment, Ventilation equipment, Emergency escape sets | N/A |
Hazards¶
- Oxygen deficiency
- Toxic gases (H₂S, CO)
- Restricted escape
- Flooding
- Heat stress
Environmental Impacts¶
- Ventilation exhaust
- Emergency discharge
Customer Impacts¶
- Service interruption
- Access restrictions
Training Required¶
- Confined space training (low risk)
- Gas monitor use
- Emergency procedures
Additional Plant and Equipment¶
- Personal gas monitors
- Safety harness if required
- Adequate lighting
- Rescue equipment on standby
Permits Required¶
Confined space entry permit required for all entries
COSHH Assessment Required¶
- Assessment of potential atmospheric hazards
- Cleaning chemical assessments
Sequence of Operations and Control Methods¶
Pre-Entry Procedures¶
- Complete confined space permit
- Identify all hazards
- Isolate all services
- Test atmosphere from outside
- Leave monitor in space for minimum 5 minutes
- Check readings:
- Oxygen: 19.5% - 23.5%
- LEL: 0%
- H₂S: <5ppm
- CO: <30ppm
Permit Requirements¶
- Authorized person to complete permit
- Define work scope clearly
- List all precautions
- Specify emergency arrangements
- Set time limits
- Display at entry point
Entry Procedures¶
- Never work alone - minimum two persons
- Continuous gas monitoring throughout
- Maintain communication with surface
- Secure safe access/egress route
- Ventilation running continuously
- Emergency plan understood by all
During Work¶
- Monitor for condition changes
- Watch for water ingress
- Check gas monitor regularly
- Evacuate immediately if alarm sounds
- Take regular breaks outside
- No petrol/diesel equipment inside
- Only intrinsically safe electrical equipment
Emergency Procedures¶
- Self-rescue is priority
- Evacuate on any alarm
- Raise alarm immediately
- Never enter to rescue without proper equipment
- Follow specific rescue plan
- Call emergency services if required
Post-Work¶
- Remove all equipment
- Conduct final gas test
- Sign off permit
- Secure space against entry
- Review any incidents
Related Risk Assessments¶
Related Documents¶
- Confined Spaces Regulations 1997
- HSE Guidance L101 - Safe work in confined spaces