Method Statement 3.3 — Excavation¶
Document Information
| Field | Value |
|---|---|
| Document Reference | MS 3.3 |
| Issue Number | 2 |
| Issue Date | 1 June 2026 |
| Next Review | 1 June 2027 |
| Prepared By | Sean Ashton |
| Approved By | Aaron Mason, Director |
Task summary¶
| Task No | Task | PPE | Plant required |
|---|---|---|---|
| 3.3 | Excavation | As defined by on-site risk assessment | Cable avoidance equipment, works vehicle and equipment, mini excavator, dumper, Stihl saw, compressor / power pack and hand tools |
Hazards¶
- Utilities exposed (underground & overhead)
- Unstable ground
- Traffic
- Manual handling
- Plant and equipment
- Animal urine (Weil's disease)
- Confined spaces
- Hand-arm vibration (HAVS)
- Dewatering excavations
- Material waste / storage
- Undermining structures
- Weather
- Pedestrians
Environmental impacts¶
- Noise
- Dust
- Silty water
- Light from night work
- Waste disposal
- Water pollution
- Animals and plants
- Excavated spoil and waste
- Carbon emissions
- Vibration nuisance
- Archaeological / protected sites (SSSI)
Customer impacts¶
- Noise
- Dust
- Access / egress
- Light
- Vibration nuisance
Training required¶
As per specific contract training matrix.
Additional plant and equipment¶
- Shoring equipment
- Excavators
- Dumpers
- Lifting equipment
- Mechanical excavator
Permits required¶
As per specific contract specifications and client requirements.
COSHH assessment required¶
- 2-stroke oil
- Diesel / petrol
- Line marker spray
- Lubricating spray
- Shoring fluid
Sequence of operations and control methods¶
- For the duration of the excavation process, monitor for in-ground utilities using the CAT & Genny.
- Monitor ground conditions and keep heavy plant away from the trench edge.
- Only use mechanical excavators where the position of underground plant is known and not within 0.5 m of underground plant.
- Do not disturb thrust blocks.
- Support all exposed plant.
- Competent banksperson to be used at all times whilst excavating.
- If ground conditions dictate or excavation exceeds 1.2 m, complete a site-specific risk assessment for trench support.
- If trench support is required, it must be installed by a competent person. Refer to supervisor / line manager for an approved safe system of work.
- All excavations must have adequate means of access and egress including a secured certificated ladder if required.
- If bridging excavations with steel road plates or trench link, contact your supervisor to arrange the appropriate size and plate thickness.
- Plates shall comply with skid-resistance requirements as indicated in the Safety at Street Works and Road Works booklet. Do not work under road plates.
- Ensure plates overlap at least 600 mm either side of the trench, secure plates so they do not move, and provide a tarmac ramp to the plates for vehicles to enter and exit.
- Display a ramp sign.
- Support trench if necessary.
- Check wheels of vehicles will have at least 250 mm to edge of plate to run along.
- If unsuitable ground is encountered or the excavation becomes unstable, stop work and inform the supervisor.