Method Statement 3.11.2 - Commissioning of Mains and Services¶
Document Information
| Field | Value |
|---|---|
| Document Reference | MS 3.11.2 |
| Issue Number | 2 |
| Issue Date | 1 June 2026 |
| Next Review | 1 June 2027 |
| Prepared By | Sean Ashton |
| Approved By | Aaron Mason, Director |
| Task No | Task | PPE to be worn | Plant required | Reference is made to the Team Pack risk assessment |
|---|---|---|---|---|
| 3.11.2 | Commissioning of Mains and Services | As defined by on-site risk assessment | Works vehicle and hand tools | N/A |
Hazards¶
- Manual Handling
- Stored Energy in the Pipe
- Defective Plant and Equipment
- Towing Techniques
- Incorrect Loading
- Insufficient Space
Environmental Impacts¶
- Noise
- Dust
- Light From Night working
Customer Impacts¶
- Noise
- Dust
- Access
Training Required¶
As Per specific contract training matrix
Additional Plant and Equipment¶
- Winch/Tractor Winch
- Pipe Bursting/Slip Lining Rig
- Mechanical Excavator
Permits Required¶
As Per specific contract specifications and Client requirements
COSHH Assessment Required¶
- 2 Stroke Oil
- Diesel/Petrol
- Line Marker Spray
- Lubricating Spray
Sequence of Operations and Control Methods¶
Mains Connections-Shut down¶
- The Supervisor shall ensure that Procedures for shutting down the parent main have been followed in line with the Water Network owner.
- Caliper the parent main to determine the correct size and ensure all fittings are on site.
- When the main has been shut down, cut out the parent main section as required using the correct cutters.
- Spray all the fittings with Chlorus as well as any cut surfaces and complete the connection.
- Re-commission the parent main and check all new work for soundness.
Mains Connection-Under pressure Tee¶
The Supervisor shall ensure that all Water Network Owner procedures relating to this operation have been followed prior to work starting
Check the pressure in the main to ensure that the correct main is being worked on and caliper the main to determine the correct size
- Check the valve for the operation is fit for purpose and the correct size
- Check the Under pressure Tee is fit for purpose and the correct size
- Spray the under pressure tee with Chlorus
- Clean the main, check for no porosity, fit and support the under pressure tee
- Spray the valve with Chlorus
- Fit the valve to the tee, support and leave in the open position
- Spray the Drill with Chlorus, immediately fit and support the Drill onto the valve on the under pressure tee, check the drill and pilot will travel through the valve
- Test the drill and valve with air from a hand pump at 1.5 times working pressure for 15 minutes
- Drill the parent main, monitor the pressure, withdraw the drill and close the valve
- Withdraw the drill body and remove the coupon
- Connect to the new main and check all new work for soundness
Mains commissioning¶
- Locate the sampling points, the preferred points are a ferrule plus pipe work and valve
- Hydrants
- Samples shall be taken by personnel who have been trained in sampling techniques
- Samples shall be taken at terminal points, branches and selected points along the route as deemed necessary
| Length of main | Sampling required |
|---|---|
| Less than 100m | 1 |
| 100m-300m | 3 |
| over 1000m | 5 |
- Samples shall be refrigerated and submitted to the Laboratory within 24hrs of sampling
Mains shall only be commissioned once all the samples have been passed, flushing water shall be appropriately discharged.
- Open the vent(s) on the test piece(s) of the new main
- Slowly open the valve on the parent main, flush the new main for 5 minutes
- Slowly close the vent(s) at the flushing point(s) and allow the pressure in the new main to equalise to that in the parent main
- Fully open valve on parent main
- Remove all temporary fittings and gauges
- Check all new work for soundness
Service commissioning¶
Under Pressure ferrule connection-Strap Ferrule¶
- The team leader shall ensure that the excavation is sufficiently deeper than the main to allow the cleaning procedure to be followed
- Once the main has been cleaned the strap ferrule will be attached ensuring that it is evenly tightened. The ferrule stopper will then be withdrawn and then installed within the drill stopper mounting
- The team leader will ensure that the minimum distance between ferrules is observed at all times (up to 150mm - 3xdiameter, over 200mm - 2xdiameter)
- On selecting the correct cutting tool the drill will be assembled on the ferrule ensuring that the valve is in the open position. The operator will then drill through the ferrule to the full depth of the cut
- The cutter will then be withdrawn and the drill valve will be closed prior to installing the stopper-mounting tool.
- The valve will then be opened and the ferrule stopper will be installed
- The team leader shall remove the drill from the excavations and make the connection to the new service pipe ensuring that all fittings, tools etc have been sprayed/dropped ion chloros solution prior to use
- The stopper will be lifted in order to commission and flush the service. At which time the fittings/service will be checked for leaks. If no leaks are visually apparent the excavation(s) will then be backfilled and reinstated
Under Pressure ferrule connection¶
- In order to execute this activity, the following equipment will be required: Appropriate drilling machine(0.5"-1" Talbot 1 or similar) 110 volt generator
- Appropriate ferrule (1" - 1.25" Talbot 2, 1.5" - 2" Talbot 3 or similar
- The Supervisor shall ensure that the respective items of equipment are within calibration prior to use
- The team leader will ensure that the excavation is sufficiently deeper than the main to allow the cleaning procedure to be followed and attachment of the chain
- Once the main has been cleaned the correct mounting saddle will be selected and the drill and ferrule will be loaded into the machine. A check will be made to ensure that the ferrule is in the closed position
- The drilling machine will then be set up on the main ensuring that the securing chains are evenly tightened the main will then be drilled and tapped with the swivel-locking pin in position. Once completed the drill will be withdrawn and the main tapped.
- The swivel-locking pin will then be removed and rotated through 180 degrees at which time the ferrule will be installed. Venting the drill set will then complete the installation
- Once the drilling machine is removed from the excavation the required fittings etc that are to be connected to the service will be sprayed/dipped in chloros solution prior to installation.
- The stopper will be lifted in order to commission and flush the service. At which time the fittings/service will be checked for leaks. If no leaks are visually apparent the excavation(s) will then be backfilled and reinstated
Related Risk Assessments¶
- RA19 — Under Pressure Drilling and Tapping Operations - Covers specific hazards and controls for drilling operations
- RA06 — Repairing & Replacing Asbestos Cement Pipes Risk Assessment - Relevant for asbestos cement mains
- RA11 — Mechanical Handling - Lifting Operations - Applicable when mechanical equipment used
- RA03 — Underground Services Risk Assessment - Essential for service identification and protection
Related Documents¶
- MS 3.6 — Disinfection of Mains
- MS 3.10 — Cutting and Disposal of Asbestos Cement Pipe
- EN 166 1B349: Eye Protection Standard
- Category B Non-Licensed Asbestos Training Requirements
- Control of Asbestos Regulations 2012