Method Statement 3.14 - Meter Installation¶
Document Information
| Field | Value |
|---|---|
| Document Reference | MS 3.14 |
| Issue Number | 2 |
| Issue Date | 1 June 2026 |
| Next Review | 1 June 2027 |
| Prepared By | Sean Ashton |
| Approved By | Aaron Mason, Director |
| Task No | Task | PPE to be worn | Plant required | Reference is made to the Team Pack |
|---|---|---|---|---|
| 3.14 | Meter Installation | As defined by on-site risk assessment | Works vehicle and hand tools. Directional drilling rig, Waste water bowser, pipe trailer and pump. | N/A |
Hazards¶
- Manual Handling
- Stored Energy in the Pipe
- Noise
- Dust
- Defective Plant and Equipment
- Towing Techniques
- Incorrect Loading
- Insufficient Space
Environmental Impacts¶
- Noise
- Dust
- Light From Night working
Customer Impacts¶
- Noise
- Dust
- Access
Training Required¶
As Per specific contract training matrix
Additional Plant and Equipment¶
- Winch/Tractor Winch
- Pipe Bursting/Slip Lining Rig
- Mechanical Excavator
Permits Required¶
As Per specific contract specifications and Client requirements.
COSHH Assessment Required¶
- 2 Stroke Oil
- Diesel/Petrol
- Line Marker Spray
- Lubricating Spray
Sequence of Operations and Control Methods¶
Pre-Installation Planning¶
- Review all relevant drawings and specifications for meter location and type
- Confirm meter size, type and specification matches design requirements
- Verify customer notification has been completed for any planned interruption
- Check all required materials are available including meter, fittings, and sealing compounds
- Ensure meter has been tested and calibrated with valid certification
Site Setup and Safety¶
- Arrive on site and park vehicles in safe location
- Set up traffic management and barriers in accordance with Chapter 8 requirements
- Complete site-specific risk assessment and Permit to Dig documentation
- Use CAT and Genny to locate and mark all services in work area
- Set up appropriate signage and customer information notices
Service Location and Excavation¶
- Hand dig trial holes to locate existing service pipe
- Carefully expose pipework maintaining minimum 500mm clearance
- Support exposed services with appropriate supports at maximum 1m intervals
- If excavation exceeds 1.2m depth, install trench support system
- Ensure excavation is sufficient size to allow safe working around meter location
Isolation and Depressurization¶
- Locate and operate upstream isolation valve following Network procedures
- Confirm isolation is effective using pressure gauge
- Open downstream tap or valve to depressurize and drain section
- Allow sufficient time for complete drainage before proceeding
- Place warning notices on isolation valves
Meter Installation - Domestic¶
- Clean pipe ends thoroughly removing any debris or corrosion
- Check meter flow direction arrow matches intended flow
- Install meter with appropriate unions or couplings ensuring correct alignment
- Fit isolation valves either side of meter if not already present
- Ensure meter is adequately supported and not under stress
- Install meter box or chamber ensuring adequate access for reading
Meter Installation - Commercial/Large Meters¶
- Verify meter manifold/bypass arrangement if specified
- Install strainer upstream of meter to prevent debris damage
- Fit pressure test points before and after meter if required
- Install non-return valve downstream if specified
- Ensure straight pipe lengths upstream (10x diameter) and downstream (5x diameter)
- Check all gaskets and seals are correctly positioned
- Tighten flange bolts in diagonal sequence to manufacturer's torque specifications
Commissioning and Testing¶
- Slowly open upstream valve checking for leaks
- Gradually fill meter and pipework removing air through test cock
- Once full, open downstream valve to establish flow
- Check all joints and connections for leaks
- Verify meter operation by running water and checking register movement
- Record initial meter reading and serial number
- Test remote reading equipment if fitted
Water Quality Procedures¶
- Spray/swab all fittings with chlorine solution (50mg/l) before installation
- Flush pipework thoroughly until water runs clear
- Take water sample for bacteriological analysis if required
- Continue flushing until chlorine residual matches supply main
- Do not leave meter in service until water quality confirmed satisfactory
Final Checks and Reinstatement¶
- Photograph completed installation for records
- Complete meter installation certificate with all details:
- Location and address
- Meter serial number
- Initial reading
- Size and type
- Date and time of installation
- Backfill excavation in 150mm layers with appropriate material
- Compact each layer to prevent settlement
- Reinstate surface to original specification
- Remove all equipment and excess materials from site
Documentation¶
- Complete and submit meter installation record
- Update network records with meter location
- Provide customer with meter details and reading
- Submit any water quality test results
- File calibration certificate with installation records
Special Considerations¶
For Internal Meters:
- Ensure adequate ventilation during work
- Protect customer property with dust sheets
- Maintain cleanliness and minimize disruption
- Ensure meter remains accessible for reading
- Check compliance with Water Regulations for location
For Boundary Box Installations:
- Ensure cover is at correct finished ground level
- Box must be secured to prevent movement
- Install with adequate drainage to prevent flooding
- Mark location clearly for future access
For AMR/Smart Meters:
- Test signal strength before finalizing location
- Program meter with correct customer details
- Verify remote reading functioning correctly
- Record all electronic ID numbers
- Provide customer with any required information
Quality Checks¶
- Meter correctly sized for application
- Flow direction correct
- No stress on pipework or meter
- All joints watertight
- Meter register clearly visible and readable
- Remote reading (if fitted) operational
- Water quality satisfactory
- Customer supply restored
Related Risk Assessments¶
- RA10 — Manual Handling - Relevant for handling meter units and associated pipework
- RA01 — Excavation - up to 1.2m deep - Required for accessing meter location
- RA16 — Hygiene - Critical for water network operations
- RA19 — Under Pressure Drilling and Tapping Operations - May be relevant for service connections
Related Documents¶
- MS 3.11.2 — Commissioning of Mains and Services
- MS 3.12 — Repair of Ductile Iron & PVC or HPPE Main
- MS 2.9 — Excavation
- Water Supply (Water Quality) Regulations
- EUSR National Water Hygiene Card Requirements